"When Communication Gets Ahead of Delivery" against green background

When Communication Gets Ahead of Delivery

Mohammed Bin Tarjim:

In 2010, Crossrail Ltd and its joint public sponsors, the Department for Transport and Transport for London, set December 2018 as the opening date for the central section of London’s new railway. Eight years later, in August 2018, Crossrail announced that the date would not be met.

The UK National Audit Office later found that the fixed completion date had shaped decision-making across the programme. Pursuing it compressed the schedule, encouraged activities to run in parallel and increased delivery risk. The report also found that Crossrail did not begin producing a sufficiently detailed, realistic delivery plan against which overall progress could be tracked until late 2018. Before then, important interdependencies across the programme were not adequately reflected in the plan.

Crossrail’s difficulties were not caused by communication. They involved planning, integration, contracts, delivery and governance. But the case raises an additional question for communication leaders: What happens when a public commitment becomes more certain than the organisation’s evidence for delivering it?

Once a date or number enters the public domain, its status changes. An internal assumption can become an external reference point. Stakeholders may plan around it, political expectations may form around it, and future changes may be judged against it. Communication therefore does more than describe organisational reality. At times, it changes the conditions under which the organisation must operate. That makes timing a strategic question, not simply a publishing decision.

Not every statement carries the same weight

A useful starting point is to distinguish between three forms of public claim. A vision or aspiration describes a direction or desired future. It can be ambitious without implying that every delivery variable has been settled. A forecast or estimate reflects the best available evidence at a given point, but remains subject to revision as that evidence changes. A public commitment is different. It is a date, number or outcome that stakeholders can reasonably expect the organisation to deliver, and whose revision carries a cost in trust, reputation or political capital.

These categories are often blurred. A planning date appears in a presentation. The presentation becomes public. The date enters headlines. Soon, a working assumption is being treated as a promise.

My own experience in government communication, including serving as spokesperson for Saudi Arabia’s Ministry of Housing, reinforced a simple lesson: the public hears a date as a promise, even when the organisation may still see it as a working assumption.

The problem is therefore not communication itself. It is allowing the strength of the public claim to exceed the maturity of the evidence behind it. There is also an ethical dimension. A public commitment is not merely a communications asset. People may organise expectations, decisions and sometimes their lives around what governments and major organisations announce. The cost of getting it wrong can extend well beyond reputation.

A hypothesis called EARNED

This is the problem behind EARNED, a practitioner-developed hypothesis I am preparing to test. The name reflects its central question: Has the organisation earned the commitment it is about to make?

Its six stages are Endorse, Align, Realize, Narrate, Enable and Debut. Endorse focuses on the approvals, legitimacy and financing needed for progress. Align supports coordination among those designing and preparing to deliver. Realize focuses on evidence that execution capability is becoming real. Narrate marks the point at which sufficiently mature commitments can enter open public communication. Enable prepares users and beneficiaries to act. Debut supports launch, early operation and the transition from promise to experience.

Narrate does not mean that public communication begins only at that stage. Projects may communicate from the beginning. It refers specifically to the point at which commitments become ready for unrestricted public communication.

EARNED is not intended to replace project governance, project controls or established management frameworks. It sits alongside them and focuses narrowly on communication, disclosure and readiness for public commitment. It can also be applied at the level of an individual asset or commitment. A phased programme may have one asset in operation, another under construction and a third still in design. Treating the entire programme as if it occupied one stage would make little sense.

The Announcement Readiness Gate

At the centre of the model is an Announcement Readiness Gate. The current hypothesis proposes three minimum areas of evidence.

The first is financial confidence. An intention to obtain financing is not equivalent to formally committed funding.

The second is schedule confidence. An approved date is not enough by itself. There should be documented evidence that the dates being turned into public commitments have a credible basis.

The third is critical stakeholder readiness. This does not mean that affected stakeholders must agree with the project or that opposition must disappear. It means that material impacts are understood, required consultation has taken place, mitigation measures and responsibilities are defined, and appropriate grievance or resolution mechanisms exist.

Other evidence will differ by project. A transport programme, a tourism destination and a technology platform will not demonstrate delivery maturity in the same way. The principle is simpler than the mechanics: Communication should not manufacture certainty that the organisation itself does not possess.

Bent Flyvbjerg’s research on major projects has documented how optimism bias and strategic misrepresentation can distort forecasts and decisions. EARNED approaches a related issue from the communication side: when should an uncertain internal forecast be allowed to acquire the status of an external commitment?

Sometimes early disclosure is exactly the right decision

Early announcement is not inherently a mistake. A government may need to communicate a long-term vision to build political support. A project may need visibility to attract capital. A developer may need to establish market demand. An organisation may need to signal commitment before every delivery variable is settled. In some markets, early communication may be essential to creating the conditions that make the project possible.

EARNED should not prevent those decisions. It should make their consequences explicit. Even then, the distinction between vision, forecast and commitment remains important. Early exposure may serve a strategic purpose without requiring an immature cost estimate or opening date to be presented as a promise.

A hard public deadline can also create useful pressure. In evidence to the UK Parliament’s Public Accounts Committee, former Crossrail chief executive Andrew Wolstenholme explained that the programme repeatedly examined whether delay would reduce risk, but concluded that delay would add cost. He argued that, because Crossrail involved a very large number of suppliers in different combinations, carrying the programme for longer created significant overhead, making the shortest viable programme the most economical.

That argument deserves to be taken seriously. The issue is not whether pressure is useful. The issue is what happens when the public commitment stays fixed after the evidence supporting it has weakened. A demanding date may create discipline up to a point. Beyond that point, maintaining it can encourage behaviours that increase cost or risk. The challenge is knowing when the evidence has crossed that line.

And the alternative is not silence

If organisations interpret readiness too conservatively, they can create an information vacuum. Major projects are highly visible. Employees talk, contractors talk, communities observe construction, journalists investigate and documents leak. If the organisation says nothing, others will fill the gap.

EARNED therefore should not be understood as a choice between silence and announcement. It is a discipline for matching the strength of a public claim to the maturity of the evidence behind it. An organisation can communicate what it knows, what remains uncertain, what is changing and when greater certainty is expected, without converting uncertainty into a promise.

It also helps to distinguish three different communication obligations. Stakeholder engagement and consultation may need to begin very early. Mandatory or urgent disclosure may be required by regulation, safety, investor rights or the rights of affected parties regardless of project stage. Publicity and voluntary public commitments are different again, because they involve choices about how broadly and how firmly the organisation presents its plans. Readiness should never become an excuse for withholding information that people are entitled to receive.

The gate does not solve the problem of power

In practice, communication leaders rarely own the final decision. A minister may need an announcement for political reasons. A CEO may see first-mover advantage. A board may prioritise a financing event. A project sponsor may decide that momentum matters more than uncertainty. A gate cannot remove those realities. What it can do is make them visible.

If leadership decides to proceed before readiness conditions have been met, the unmet conditions, the uncertainty and the accepted risks should form part of the decision record.

Leadership can override the gate. It should not be able to override the evidence.

The gate does not solve the problem of authority. It exposes it. The important question is not simply whether the gate is passed, but who accepts the risk of passing it when readiness conditions are not met. That changes the conversation.

“Communications does not think we are ready” is easy to dismiss. “Funding is secured, stakeholder processes are in place, but the evidence supporting the public opening date remains below the agreed confidence threshold” is a governance discussion.

Three questions before a major announcement

For communication leaders, the practical test can begin with three questions:

  1. What are we turning from an internal assumption into a public commitment?
  2. What evidence tells us the organisation can sustain that commitment?
  3. What becomes harder to change once we say it publicly?

If the answers are weak, communication may be exposing a delivery or governance problem that deserves attention before the announcement. This is where communication can create value, not by claiming ownership of the decision, but by improving its quality.

Testing the hypothesis

EARNED now needs evidence more than additional theory. The planned test is retrospective and comparative. It should include both successful and troubled projects across infrastructure, transport, tourism, real estate, energy, culture and technology, rather than selecting failures that conveniently support the model.

Cases should be useful only where there is enough public documentation to reconstruct three things: the announcement decision, the evidence available at the time, and the later outcome. The test is straightforward: Would EARNED have changed an actual communication decision using only information that was available at the time? Would that change have improved the project’s ability to progress, reduced an expectation gap or prevented unnecessary risk? Or would the model have delayed communication that was strategically necessary?

The objective is not to confirm the model. It is to identify the conditions under which it fails. If EARNED can only explain outcomes after the event, its value is analytical. If it helps leaders make better decisions before commitments are made, then it begins to have managerial value.

If you have led communication on a major project and can identify a case in which EARNED would have produced the wrong decision, I would like to hear it. Those cases are particularly valuable because they can help establish where the model’s boundaries actually lie.

Communication already shapes the environment in which major projects succeed or struggle. The profession should therefore contribute not only to how commitments are communicated, but to the quality of the decision to make them.

Before the next major announcement, there is one question worth asking:

Has the organisation earned the commitment it is about to make?

+++

Mohammed Bin Tarjim is a Saudi strategic communication, reputation and crisis advisor with more than two decades of experience advising ministries, government-owned companies and boards. A former spokesperson for Saudi Arabia’s Ministry of Housing, his work focuses on communication strategy, reputation, crisis management, stakeholder relationships and the role of communication in organisational decision-making. He is developing EARNED, a practitioner model for disclosure and announcement governance in major projects.